  PURSAKLAR PORTABLE WATER TRAETMENT PLANT
     
 
  Scope of work
  Civil works, local equipment and material supply, erection of all the equipment, erection supervision and commisioning of the plant.
  Client
  General Direktorate of State Hydraulic Works
   
   
   
   
  Capacity
  75,000m3/day
  Process units
  1 Flash mixer, 4 Flocculation mixers, 4 Multiflo clarifiers, 6 sand filters, Reagent building [FeCI3, NaOH, KMnO4, Polyelectrolyte], Chlorination (pre, break-point & post-chlorination)Contact Tank 3500 m3 treated water tank,
2x500 m3 backwash water recovery tank,
2x1000kVA transformer station

 PURSAKLAR PORTABLE WATER TRAETMENT PLANT

 